Progress of watershed projects are as : 

(Rs. in Crore and Area in Hactare)

S.No. Financial Year Opening Balance Fund received Total available fund Expenditure Area Treated
1 2009-10 0.00 77.69 77.69 0.00 0
2 2010-11 77.69 285.77 363.46 36.24 0
3 2011-12 327.22 354.02 681.24 86.72 10918
4 2012-13 594.52 471.70 1066.22 217.82 136813
5 2013-14 848.36 0.00 848.36 509.52 363063
6 2014-15 338.84 447.87 786.71 709.04 491597
7 2015-16 77.67 400.00 477.67 361.97 253771
8 2016-17  115.70 490.62 606.32 486.54 411467
9 2017-18 119.78 319.50 439.28 288.03 166667
10 2018-19 (upto May 2018) 151.25 51.61 202.86 110.60