Physical Progress  of CAD Bisalpur Project

 

S.No.

Financial Year

Orignal target (Ha.)

Revised target (Ha)

Actual Progress (Ha.)

1

2008-09

3500

3500

3041

2

2009-10

20000

12500

12558

3

2010-11

16000

16000

16006

4

2011-12

14000

10000

10029

5

2012-13

14000

7000

5606

6

2013-14

14000

5200

3990

7

2014-15

12000

4200

2163

8

2015-16

10000

6200

4382

9

2016-17 upto Jan-17

10000

0.00

1429